Replacing a Flat Roof

SR Bell were called out to a leaking roof in Lancashire. When we arrived we found that the roof wasn’t only poorly maintained, it was obvious that the issues had been caused by some really bad workmanship.

Roof Structure Carpentry

The leaking felt had caused water damage to the roof timbers. Once we uncovered replaced old timbers, fitted rigid insulation and new 18mm hardwood ply.

Sika Single Ply Membrane System

The front flat felt roof was replaced with a Sika Sarnafil single ply membrane system.

After seeing the state of the dormer roof, the customer decided that they would also like us to replace the back pitched dormer roof.

The project was completed in June 2019 over a 5 week duration. SR Bell managed the project requirements from start to finish, including the employment of various sub-contractors. All waste was properly disposed of by SR Bell using skips.

The final project was completed for the customer within the estimated time frame and on budget. Building and planning was submitted to Chorley borough council and local inspectors inspected and signed off the work completed. We also used our own structural engineer throughout.